Event / Incident Location
|
|
209 N VENICE BLVD
|
Time of Incident Update
|
|
07:20 pm
|
Activity update
|
|
ONCE UNCOVERED COMPLETELY THE SEWER MAIN TURNED OUT TO BE A LARGER SIZE THAN THEY ANTICIPATED ACCORDING TO THEIR PRINTS. THE CONTRACTOR CAN NOT OBTAIN THE CORRECT SIZE UNTIL TOMORROW. THEY WILL INSTALL A BYPASS ON THE SEWER MAIN FOR TONIGHT, THE EXCAVATION WILL BE FENCED OFF AND A LEAK CREW WILL WATCH THE EXCAVATION OVER NIGHT. CONTRACTOR WILL RETURN TOMORROW MORNING WITH THE CORRECT MATERIAL TO COMPLETE SEWER MAIN REPAIR.
|
Incident Commander
|
|
JOSE LUCERO
|
Cell phone number
|
|
(213) 840-1224
|
Responsible Manager
|
|
JUSTIN RYAN
|
Manager phone number
|
|
213-792-5476
|
|