Event / Incident Location
|
| |
2960 Wilshire Blvd.
|
|
Time of incident update
|
| |
08:19 pm
|
|
Activity update
|
| |
As of 2/28/19 at approximately 2pm, the leak was stopped by installing a 30” inch Bell Clamp on the break near the 30” Bell. The District is scheduling a planned shut off for this coming Thursday, 3/7/19 to make permanent repairs. We will cut out and replace approximately 4’ feet of pipe. The job site is safe and clean.
|
|
Incident Commander
|
| |
Caesar Rubio
|
|
Cell phone number
|
| |
(213) 792-6220
|
|
Additional Notes
|
| |
none
|
|
This report submitted by
|
| |
Joni J Quinn
|
|
Submitter's contact phone
|
| |
213-367/6821
|
|
Responsible Manager
|
| |
Joseph Mundine
|
|
Manager phone number
|
| |
213-792-8485
|
|