Event / Incident Location
|
| |
2960 Wilshire Blvd.
|
|
Time of incident update
|
| |
06:10 am
|
|
Activity update
|
| |
We have confirmation that the 30″ mechanical couplings from Smith -Blair will be delivered this Tuesday, 03/12/19. We are planning to schedule the work on Thursday, 03/14/19. The planned Shut off will be scheduled from 6:00pm-5:00am. We will backfill with Slurry and continue to monitor the steel plates until paving is scheduled.
|
|
Incident Commander
|
| |
Mr. Caesar Rubio
|
|
Cell phone number
|
| |
(213) 792-6220
|
|
Additional Notes
|
| |
None
|
|
This report submitted by
|
| |
R. Hamada
|
|
Submitter's contact phone
|
| |
(213) 367-6821
|
|
Responsible Manager
|
| |
Mr. Joe Mundine
|
|
Manager phone number
|
| |
(213) 792-8485
|
|