Event / Incident Location
|
| |
9460 Sunland Blvd
|
|
Time of Incident Update
|
| |
02:58 am
|
|
Activity update
|
| |
Pumper Group could not resolve the I.S.P. issue. Welders were able to patch the 12 Inch Pipe. DWP crew was unable to replace the 12 Inch Gate Valve and currently filling in the 24 Inch Main.
|
|
Incident Commander
|
| |
Jose Arias
|
|
Cell phone number
|
| |
(626) 888-0864
|
|
Additional Notes
|
| |
Additional Updates to follow
|
|
This report submitted by
|
| |
R. Hamada
|
|
Submitter's contact phone
|
| |
(213) 367-6821
|
|
Responsible Manager
|
| |
Rigoberto Morelos
|
|
Manager phone number
|
| |
(213) 798-5278
|